Progress on new Warragul indoor sports stadium for Baw Baw Shire
Early works are progressing well on site at the Warragul Leisure Centre in preparation for major construction of a new indoor multi-use sports stadium.
Locally based Kubale Constructions has taken control of the site to complete the preparatory works contract which includes asbestos removal, earthworks, storm water drain installation and sewer diversion. So far approximately 40 percent of asbestos abatement works have been safely completed without issue. A full-time independent hygienist has been on site monitoring contractor methodology and air quality throughout the abatement process, which will remediate and 'make safe' the site for the expansion of the indoor sports stadium.
Critical asbestos abatement works underway under close supervision by hygienist professionals
Changing room improvements
Additionally electrical conduits have been installed parallel to the existing outdoor pool in preparation for the new facility. Next steps will see installation of new stormwater pipework, sewer diversion works, demolition and removal of redundant infrastructure, as well as site preparation and compaction ahead of the main construction commencement.
The contract for the main construction of the new stadium is set to be awarded at the end of May, with construction to commence soon after. Once complete, the new indoor stadium will expand capacity from two to four indoor multi-use courts and feature a link to the existing building, a new cafe and kitchen, storage spaces, Changing Places accessible change room, and a large car park.
Further earthworks underway to prepare the site for underground electricity, sewer and storm water diversion works
Stadium expansion
This $10 million project is being developed by Baw Baw Shire Council in partnership with the Victorian Government who are contributing $6 million towards the project. Council is contributing the remaining $4 million through its Capital Works Program. The project is due for completion by mid-2023. For more project details go to Warragul Leisure Centre Stadium Expansion.
Indoor courts for better service
Mayor Cr Michael Leaney said, "It's great to see works on the ground progressing for this project. These early works are an important step in safely preparing the site for construction of the new two indoor courts needed to better service increased demand for indoor sports in Baw Baw. We look forward to more progress on-site in the near future."
Architects render of the facility due for completion in 2023
Pictures from Baw Baw Shire Council website.
Source: http://gippsland.com/
Published by: news@gippsland.com
Latest News
Darren Chester calls for stop to rural health merger citing risks to Gippsland services due to lack of consultation, secrecy and autonomy lossNicholson Primary School students get chance to discuss Parliament while receiving certificates from Darren Chester
Russell Broadbent urges government budget accountability to alleviate cost-of-living pressure to tackle inflation and alleviate cost-of-living pressures following the Reserve Bank decision
Senators to reject Fresh food tax after report reveals lack of clarity and adverse impact on farmers and families
APS Drainage and Civil selected for culvert relining on Loch-Kernot Road in Bass Coast Shire from 13 May 2024 with $750,000 budget
Community feedback wanted on new policy for celebrating significant dates in Baw Baw Shire by 31 May 2024
Latrobe City Candlelight Vigil honoured domestic violence in 2024
Baw Baw Shire Council meeting snapshot - Wednesday 17 April 2024
Cann River fire damages three commercial properties and burns popular Squires Cafe to ground
Community feedback wanted for the Wellington Shire Draft Budget 2024/25 by 29 May 2024